Cbs4local

TxDOT road closures happening between

E.Martin39 min ago

I-10 Widening West

Sunday, November 10

  • I-10 East will be closed at Redd Road.
  • DETOUR: Take Exit 8 (Redd Road), continue on South Desert Boulevard, and re-enter I-10 past Mesa Street.

    Crews will be placing bridge beams.

    Monday, November 11

  • I-10 West will be closed at Mesa Street.
  • DETOUR: Take Exit 11 (SH 20/Mesa Street/Thorn Avenue), continue on North Desert Boulevard, and re-enter I-10 past Redd Road.

    Crews will be placing bridge beams.

    Monday, November 11, through Saturday, November 16

  • I-10 East and West will be reduced to one lane between Vinton Road and Transmountain Road.
  • Crews will be working on retaining walls.

    Monday, November 11, through Saturday, November 16

  • I-10 East and West will be reduced to one lane between Mesa Street and Redd Road.
  • Crews will be conducting earth work and installing bridge deck panels.

    Monday, November 11, Thursday, November 14, and Friday, November 15

  • North Desert Boulevard will be reduced to one lane between the Artcraft exit ramp and the Redd Road onramp.
  • On-ramp from North Desert Boulevard to I-10 West will be closed.
  • DETOUR: Continue on North Desert and enter I-10 past Transmountain.

    Crews will be installing metal beam guard fence.

    Tuesday, November 12

  • I-10 East will be closed at Vinton Road.
  • South Desert Boulevard will be closed from Vinton Road to south of Los Mochis Drive.
  • DETOUR: Take Exit 2 (Spur 37/Vinton Road/Westway Boulevard), turn right on Vinton Road, turn left on Doniphan Road, turn left on Talbot, turn left on Spur 16, turn right on South Desert, re-enter I-10 past Transmountain Road.

  • The turnaround from North Desert Boulevard to South Desert Boulevard at Vinton Road will be closed.
  • Los Mochis Drive will be closed at South Desert Boulevard.
  • Crews will be installing bridge beams.

    I-10 Widening West 2

    Saturday, November 9 through Monday, November 11

  • I-10 East will be closed from Anthony, TX to Transmountain Road
  • DETOUR: Take Exit 0 (Anthony TX), proceed on S. Desert Blvd through the Anthony, Vinton, and Transmountain Intersections, enter I-10 east after Transmountain.
  • Crews will be placing new barriers and striping the pavement

    Monday, November 11 through Friday, November 15

  • Right lane closure on I-10 Westbound from Exit 2 (Nashua Rd) to Anthony
  • Crews will be installing asphalt pavement and storm water pollution prevention plan

    Saturday, November 16 through Monday, November 18

  • I-10 West will be closed from Transmountain Blvd. to Anthony TX
  • DETOUR: Take Exit 6A (Transmountain Rd.) proceed on N. Desert Blvd through the Vinton and Anthony Intersections, enter I-10 Westbound after Anthony, TX.

    Crews will be placing new barriers and striping the pavement

    North Mesa Street Rehabilitation Project

    Monday, November 11 through Friday, November 15

    p.m. to 6 a.m. (Night)

  • Mesa (SH-20) northbound and southbound alternating lane closures Sunland Park Drive intersection
  • Mesa Street (SH 20) and Sunland Park Intersection closure.
  • Crews will be surface milling for ride quality.

    US-54 & State Line Project

    Tuesday, November 12 through Friday, November 15

  • US-54 south- and northbound from State Line Road reduced to one lane
  • Crews will be working demolition and preparation of the new turnaround of side shoulders.

    Paisano Bridge Replacement

    Tuesday, November 12, 2024, through Tuesday, September 16, 2025

    Continuous closure

  • US-62 (Paisano) eastbound between Doniphan and Executive closed
  • Crews will be working on demolition and bridge work.

    Pedestrian Facilities Improvement Project

    Monday, November 11 through Friday, November 15

  • Paisano west- and eastbound between Boone and Val Verde right lane closed
  • Crews will be working on placement of guardrails, concrete curb, gutter, sidewalks, fencing, and drill shafts.

  • Dyer west- and eastbound between Titanic and Hercules left lane closed
  • Crews will be working on drill shaft excavation.

  • Dyer west- and eastbound between Ellerthorpe and Julian right lane closed
  • Crews will be working on trenching for conduit installation.

    US-62 Rehabilitation Project

    Wednesday, November 13 through Friday, November 15

  • East Paisano (US-62) eastbound and westbound alternating lane closures on the bridge that crossed the Union Pacific Railroad Line
  • Crews will be milling.

    North Mesa Street Lighting Improvement Project

    Monday, November 11 through Friday, November 15

  • If Needed – Mesa (SH-20) north- and southbound alternating lane closures Glory Road / East Baltimore Drive to Mesita Drive/Sun Bowl Drive
  • If Needed – Mesa (SH-20) northbound left lane closure Brentwood Avenue to Executive Center Boulevard
  • If Needed – Mesa (SH-20) southbound alternating lane closures I-10 to Crossroads Drive
  • If Needed – Mesa (SH-20) north- and southbound alternating lane closures Mesita Drive/Sun Bowl Drive to Sunland Park Drive
  • Crews will be boring for electrical conduit, pouring drill shaft foundations, potholing, installing new lighting poles, removing existing poles, electrical inspection, and Concrete sidewalk and landscape repairs.

    Traffic Signal Improvements Project

    Monday, November 11 through Friday, November 15

  • Dyer north- and southbound right lane closures at the Tetons Drive intersection
  • Dyer north and southbound right lane closures at the Hondo Pass Drive intersection
  • Dyer north- and southbound right lane closures at the Diana Drive intersection
  • Dyer north- and southbound right lane closures at the Wren Avenue intersection
  • Zaragoza north- and southbound right lane closures at Rojas Drive intersection
  • US-54 Gateway North Boulevard and Gateway South Boulevard right lane closures at Martin Luther King Boulevard/Kenworthy Street intersection
  • Crews will be working on intersection improvements.

    ITS INFRA at Zaragoza/BOTA Port of Entry

    Monday, November 11

  • Loop 375 westbound at Conception right lane closed
  • Loop 375 westbound between San Marcial and Delta shoulder closed
  • Tuesday, November 12

  • Loop 375 westbound between North San Antonio St and Paisano right turn lane closed
  • Loop 375 eastbound between San Antonio St and Gateway South right lane closed
  • Wednesday, November 13

  • Loop 375 eastbound at Paisano between San Antonio and Gateway South right lane closed
  • Loop 375 westbound after Zaragoza on-ramp right lane closed
  • Thursday, November 14

  • Paisano westbound before Gateway North right lane closed
  • Crews will be working on the installation ITS equipment.

    Guardrail Repair Project

    Tuesday, November 12

  • I-10 westbound at Anthony exit ramp complete closure
  • Wednesday, November 13

  • I-10 eastbound at Executive off-ramp left lane closed
  • Thursday, November 14

  • SH-20 (Doniphan) southbound between Moreno and Spur 16 right lane closed
  • Friday, November 15

  • I-10 westbound between Airway and Paisano right lane closed with a complete off-ramp closure on Paisano
  • Crews will be working on guardrail.

    Miscellaneous Concrete

    Tuesday, November 12 and Wednesday, November 13

  • I-10 westbound between Airway and Paisano left lane closed
  • Thursday, November 14

  • I-10 eastbound between Executive and Porfirio Diaz left lane closed
  • I-10 westbound between Santa Fe and Schuster left lane closed
  • Sunday, November 17

  • I-10 eastbound between Executive and Porfirio Diaz left lane closed
  • I-10 westbound between Santa Fe and Schuster left lane closed
  • Crews will be repairing CTB wall.

    Spall Repair Project

    Tuesday, November 12 through Thursday, November 14

  • I-10 eastbound between Schuster overpass and McRae overpass alternate lane closures
  • Crews will be working on spall repairs.

    Tuesday, November 12 and Friday, November 15

  • SH-178 (Artcraft) between Doniphan and Upper Valley alternate lane closures
  • Crews will be sealing bridge joints.

    Diamond Grinding (IH-10 & US-54)

    Tuesday, November 12 through Thursday, November 14

  • I-10 westbound between Don Haskins and Lee Trevino two right lanes closed
  • Crews will be working on diamond grinding.

    Montana Widening Project

    Friday, November 8 to Monday, November 11

    Daily, 9 a.m. to 5 p.m.

  • Montana Avenue (US 62/180) eastbound alternate lane closures between George Dieter Drive and Lee Boulevard
  • Crews will be striping on both frontage road and main lanes.

    Purple Heart 375 Widening Project

    Monday, November 11 to Friday, November 29

    Daily, 8 a.m. to 4:30 p.m.

  • Purple Heart Highway (Loop 375) north- and southbound left lane closures between Montana Avenue and Iron Medics Drive
  • Purple Heart Highway (Loop 375) north- and southbound full closure between Montana Avenue and Spur 601
  • Purple Heart Highway (Loop 375) northbound on-ramp at Montana Avenue will be closed.
  • Purple Heart Highway (Loop 375) southbound on-ramp at Spur 601 will be closed.
  • Crews will be pouring concrete for a bridge deck.

    Continuous closure until further notice

  • Purple Heart Highway north and southbound shoulder closures from Montana Avenue to Spur 601
  • Crews will be widening main lanes and constructing north and southbound frontage road.

    Loop 375 Widening Project

    Monday, November 11 to Thursday, November 14

    Nightly, 9 p.m. to 5 a.m.

  • Americas Avenue (frontage road) full closure at North Loop underpass/intersection
  • Americas Avenue (frontage road) south to north turn-around, reduced to two right lanes only up to North Loop intersection
  • Americas Avenue (frontage road) southbound Americas Avenue reduced to two right lanes only up to North Loop intersection
  • Crews will be working on installing bridge structures.

    Continuous closure, beginning Monday, November 11 to Friday, November 15

  • Americas Avenue (frontage road) southbound left lane and south to north turnaround UPRR Bridge underpass at North Loop Road
  • Americas Avenue (frontage road) northbound, north to south turnaround UPRR Bridge underpass at Alameda Avenue
  • Americas Avenue (frontage road) north- and southbound turnarounds at North Loop intersection
  • Crews will be working on installation of curb/sidewalk, guardrail, T-551 concrete barrier, and bridge structures.

    Alameda Mill and Inlay Project

    Continuous closure beginning Sunday, November 10 through Monday, November 11

  • Alameda Avenue (SH-20) at Delta intersection
  • Crews will be milling and paving.

    Monday, November 11 to Friday, November 15

    Daily, 9 a.m. to 4 p.m. and Nightly, 8 p.m. to 6 p.m.

  • Alameda Avenue (SH-20) east- and westbound alternate lane closures between Padres Drive and Glenwood Street
  • Crews will be milling, paving, and installing pavement markings.

    Horizon/Darrington Reconstruction Project

    Monday, November 11 to Friday, November 15

    Daily, 9 a.m. to 4 p.m.

  • Horizon Boulevard westbound intermittent right lane closures from Desert Mesa Drive to Thea Smith Drive
  • Horizon Boulevard eastbound intermittent right lane closure at Thea Smith
  • Crews will be installing new roadway illumination.

    Continuous closures

    Monday, March 25 until further notice

  • Horizon Boulevard westbound lane closure from Torrey Pines to Desert Mesa Drive, lanes reduced to one lane
  • Horizon Boulevard hike/bike trail from Torrey Pines to Desert Mesa Drive will be closed indefinitely.
  • Friday, June 28 until further notice

  • Horizon Boulevard westbound lane from Desert Mesa to Rodman Street will be shifted to the median and transitioned back on Rodman Street
  • Horizon Boulevard and Lago Del Esta intersection closure
  • Crews will be working on final subgrade, pavement operations and excavating ponding areas.

    Alameda Raised Medians Project

    Monday, November 11 to Friday, November 15

    Nightly, 9 p.m. to 6 a.m. and Daily, 9 a.m. to 4 p.m.

  • Alameda Avenue (SH-20) east- and westbound inside lane closures between Rio Vista Road and Passmore Road
  • Crews will be installing concrete medians and electrical items.

    Loop 375 Mill and Inlay Project

    Sunday, November 10 to Thursday, November 14

    Nightly, 7:30 p.m. to 6 a.m.

  • Joe Battle Boulevard (frontage road) north- and southbound alternating lane closures between Pellicano Drive and Montana Avenue
  • Traffic will be reduced to one lane in work areas.

    Crews will be pouring concrete sidewalks in the shoulders and striping at intersections controlled by Temporary Traffic Signals.

    Sidewalk Project

    Monday, November 11 until further notice

    Daily, 9 a.m. to 4 p.m.

  • Pan American Drive east- and westbound alternating lane closures from South Americas Avenue north- and southbound
  • Socorro Road (FM258) east- and westbound alternating lane closures from South Americas Avenue north- and southbound
  • Alameda Avenue (SH20) east- and westbound alternating lane closures from South Americas Avenue north- and southbound
  • Crews will be removing ramps and constructing sidewalks and ramps.

    Monday, October 28 until further notice

    Daily, 9 a.m. to 4 p.m.

  • Americas Avenue (frontage road) northbound alternating lane closures from Zaragoza Road to Pan American Drive
  • Crews will be removing ramps and constructing sidewalks and ramps.

    I-10 Landscape & Aesthetics Project

    Monday, November 11 to Friday, November 15

    Daily, 7 a.m. to 3:30 p.m.

  • I-10 eastbound at Lee Trevino underpass right lane and shoulder closure.
  • Gateway East Boulevard at Lee Trevino Drive left lane closed.
  • Crews will be removing concrete riprap.

    Monday, November 11 to Friday, November 15

    Daily, 9 a.m. to 4 p.m.

  • I-10 westbound at Lee Trevino underpass right lane and shoulder closure.
  • Crews will be removing concrete riprap.

  • I-10 Hudspeth Safety Rest Area
  • Monday, November 11 to Thursday, November 15

    Daily, 9 a.m. to 4 p.m.

  • I-10 east- and westbound right lane closures between Fort Hancock and McNary
  • Crews will be working on installing concrete barrier.

    Median Concrete Barrier Project

    Continuous closure until further notice

  • Montana Avenue (US 62/180) east and westbound complete left lane closure between RM 124 and RM 126 (Guadalupe Peak)
  • Traffic will be reduced to one lane in work areas.

    Closure is necessary for installation of median concrete barrier.

    RM 652 Full Depth Rehabilitation Project

    Continuous closure until further notice

  • RM 652 east and westbound alternating lane closure 8.36 miles east of FM 3541 to Reeves County Line
  • Continuous two-way traffic, one-lane work zone requiring traffic to be alternating onto one lane and controlled by Temporary Traffic Signals with a 13-foot lane width restriction.

    Closure is necessary for the construction of new roadway consisting of full depth rehabilitation.

    RM 652 Full Widening Project

    Monday, March 11 until further notice

  • RM 652 westbound lanes reduces to one lane two-way traffic from FM 3541 to Kimble Draw Bridge
  • Closure is necessary for the reconstruction of the roadway.

    0 Comments
    0